RERA explained: what the law gives homebuyers and how to complain

RERA in plain English: project registration, the 70% escrow rule, carpet area, the 10% advance cap, delay interest, 5-year defect cover and how to complain.

Finance.net.in title card: RERA explained: what the law gives homebuyers and how to complain

Key points

  • A builder cannot advertise or sell flats in a project of more than 500 square metres or more than eight apartments without registering it with the state RERA authority.
  • 70% of the money collected from buyers must sit in a separate bank account and be used only for that project's land and construction cost.
  • A builder cannot take more than 10% of the price before a written, registered agreement for sale.
  • If possession is late, you can exit with a refund plus interest, or stay and get interest for every month of delay.
  • Defects reported within five years of possession must be fixed free of charge within 30 days.

Say you have paid a builder ₹8 lakh as booking money for a ₹60 lakh flat in a project that is still a hole in the ground. Two years later the site is quiet, the sales office has shut and the builder stops answering calls. Before 2016 your choices were a slow civil suit or a consumer case. Today the first stop is RERA, the Real Estate (Regulation and Development) Act, 2016, and the regulator each state has set up under it.

This guide explains, in plain terms, what RERA requires from builders, what rights it gives you as a homebuyer, how to check a project on your state’s RERA website before you pay anything, and how to file a complaint if things go wrong. The law is central, but the regulators, websites, fees and interest rates are set state by state, so always check your own state’s rules for the final word.

What RERA is and who it covers

Parliament passed the Act in March 2016. According to the Ministry of Housing and Urban Affairs, some sections came into force on 1 May 2016 and the rest on 1 May 2017. Each state and union territory has to set up its own Real Estate Regulatory Authority, an Appellate Tribunal and adjudicating officers. The law applies to residential and commercial projects, and to private as well as public bodies that sell property.

The core idea of RERA is simple: a builder (the Act calls the builder a “promoter”) cannot advertise, market, book or sell any plot, flat or building in a project inside a planning area without first registering that project with the state authority. Real estate agents who sell in these projects also have to register.

Which projects need registration

Section 3 exempts small projects. Registration is not needed where the land to be developed is no more than 500 square metres, or the number of apartments is no more than eight, counting all phases. A state government may lower these limits. Projects that already had a completion certificate when the Act started, and pure repair or redevelopment work that involves no new sale, are also outside the registration rule. Projects that were ongoing without a completion certificate had to apply within three months of the Act starting.

The rules builders must follow under RERA

Most of the protection for buyers comes from a handful of sections. Here is what they say, in plain English.

Rule What the Act says Section
Registration No advertising, booking or sale before the project is registered 3
Separate account 70% of money collected from buyers goes into a separate account in a scheduled bank, only for land and construction cost 4(2)(l)(D)
Carpet area Flats are described by net usable floor area, a single defined measure 2(k)
Advance cap No more than 10% of the cost as advance or application fee before a written, registered agreement for sale 13(1)
Plan changes Changes to sanctioned plans need consent; major changes need written consent of at least two-thirds of allottees 14(2)
Defect liability Defects reported within five years of possession must be fixed free within 30 days 14(3)
Delay Refund with interest if you exit, or interest for every month of delay if you stay 18(1)

The 70% separate account

Before RERA, a common complaint was that money paid for one project was used to buy land for the next one. The Act now requires 70% of the amounts realised from buyers to be deposited in a separate account with a scheduled bank. That money can only cover the cost of construction and land for that project. The builder can withdraw it only in proportion to the work completed, and only after an engineer, an architect and a practising chartered accountant certify that the withdrawal matches progress.

Carpet area, not “super area”

Section 2(k) defines carpet area as the net usable floor area of a flat. It excludes the area under external walls, service shafts, an exclusive balcony or verandah and an exclusive open terrace, but it includes the area under internal partition walls. Builders used to quote “super built-up area”, which loads in a share of lobbies and staircases, and two flats with the same super area could have very different usable space. Comparing carpet area makes price per square foot a fair comparison.

Your money rights: 10% advance, interest on delay and defects

The 10% advance limit

Under section 13(1), a builder cannot take more than 10% of the cost of the flat, plot or building as an advance or application fee without first signing a written agreement for sale with you and registering it. On a ₹60 lakh flat, that means no more than ₹6 lakh before a registered agreement. If a sales team asks for 20% “to block the unit”, that is a red flag.

Interest when the builder is late

If the builder fails to hand over possession by the date in the agreement, section 18 gives you two choices. You can withdraw and claim a refund of everything you paid, with interest at the rate prescribed in your state’s rules, plus compensation. Or, if you want to keep the flat, you can stay in the project and the builder must pay you interest for every month of delay until possession.

The definition of “interest” in section 2(za) is meant to be fair both ways: the rate a builder charges you for late payment must be equal to the rate the builder pays you when it defaults. As an illustration, if you paid ₹40 lakh and your state’s prescribed rate worked out to 10% a year, a one-year delay would mean roughly ₹4 lakh of interest owed to you. Your actual rate depends on your state’s rules.

Five years of defect liability

Section 14(3) covers structural defects and defects in workmanship, quality or services promised in the agreement. If you bring such a defect to the builder’s notice within five years from the date of handing over possession, the builder must fix it without charge within 30 days. If the builder fails, you are entitled to compensation under the Act. Report defects in writing, with photographs and dates, so there is a record.

Under RERA, a builder cannot take more than 10% of the price before a registered agreement for sale.

Your duties as a buyer

RERA is not one-sided. Section 19 also lists what you must do. You must pay instalments in the manner and within the time set out in the agreement for sale, and pay your share of registration charges, municipal taxes, water and electricity charges, maintenance and similar costs. If you pay late, you are liable to pay interest at the prescribed rate, the same rate the builder would pay you. You are also expected to help form the residents’ association or society and to take physical possession once the flat is ready.

If you are taking a home loan for the purchase, line up the loan’s disbursement schedule with the builder’s payment plan. A missed demand because the bank was slow still counts as your delay. You can check how a construction-linked loan changes your EMI with the EMI calculator.

How to check a project on the state RERA website

Under section 11, a registered builder has to create a page for the project on the state authority’s website and keep it updated. The page must show the registration details and, every quarter, the number and type of flats booked, garages booked, approvals taken and pending, and the status of construction. Every advertisement or brochure must carry the authority’s website address and the project’s registration number.

Before you pay a booking amount, spend half an hour on the portal:

  1. Find the registration number on the brochure and search for it on your state RERA website. No number, or a number that does not match the project name and address, means stop.
  2. Check the promised completion date the builder declared at registration, and compare it with what the sales team tells you.
  3. Read the latest quarterly update. Compare the construction status with what you see on site.
  4. Open the approvals list. Look for the sanctioned building plan and the commencement certificate, and note which approvals are still pending.
  5. Look at how many flats are already booked. Very slow sales can mean slow construction.
  6. Search the portal for complaints and orders against the project or the builder’s other projects.
  7. Check that the agent you are dealing with has a RERA agent registration.

Filing a RERA complaint

Section 31 lets any aggrieved person file a complaint with the authority or the adjudicating officer for a breach of the Act, its rules or regulations, against a builder, a buyer or an agent. An association of allottees or a registered consumer association can also file. The form, manner and fee are set by each state’s regulations, and most states take complaints online through the same RERA portal.

Authority or adjudicating officer?

The route depends on what you want. Broadly, directions to comply with the Act, such as completing work or refunding money with interest, come from the authority, while claims for compensation under sections 12, 14, 18 and 19, such as for false information in a brochure, unfixed defects or delayed possession, go to the adjudicating officer. Your state portal usually shows which form to use for which relief. Section 71 says this officer is a judicial officer who is or has been a District Judge. The Act asks the adjudicating officer to decide a compensation application within 60 days, and to record reasons in writing if it takes longer.

Appeals

If you disagree with an order of the authority or the adjudicating officer, you can appeal to the state’s Real Estate Appellate Tribunal within 60 days of receiving the order (section 44). The tribunal can accept a late appeal if there was sufficient cause. A further appeal lies to the High Court, again within 60 days of the tribunal’s decision being communicated.

Make your complaint strong

  • Attach the registered agreement for sale, allotment letter and every payment receipt.
  • Note the promised possession date from the agreement and from the RERA registration.
  • Keep copies of emails, letters and demand notices, plus dated photographs of the site.
  • State clearly what you want: refund with interest, monthly delay interest, repairs or compensation.

Where RERA falls short

RERA gives you rights, but it cannot conjure money out of a builder that has none. If a builder is insolvent, an order for refund may take a long time to recover. Rates of interest, fees and procedures differ across states, so a friend’s experience in another state may not apply to you. And RERA covers registered projects: very small projects under the 500 square metre or eight-apartment limit, and resale flats bought from an individual owner, sit largely outside it. In those cases, careful title checks and a lawyer’s review of documents matter even more.

Under-construction flats also carry an opportunity cost. Money paid early earns nothing until you get possession, while you may be paying rent and a pre-EMI on a loan at the same time. Budget for both.

Key takeaways

  • Only book in a project with a valid registration number that matches the state RERA website.
  • Pay no more than 10% of the cost before a written, registered agreement for sale.
  • Compare flats by carpet area, as defined in RERA, not by super built-up area.
  • If possession is late, you can exit with a refund and interest, or stay and claim interest for every month of delay.
  • Report defects in writing within five years of possession; the builder must fix them free within 30 days.
  • Complaints go to the state authority or adjudicating officer; appeals go to the Appellate Tribunal within 60 days.

This is general information, not legal advice. For a large purchase, have a property lawyer read the agreement for sale before you sign it.

What it means for you

Before paying any booking amount, check the project's registration and quarterly updates on your state RERA website. If the builder delays or delivers defects, you have a statutory claim for interest, refund or repairs.

EMI Calculator

Frequently asked questions

Which projects must be registered under RERA?

Any project in a planning area where the land exceeds 500 square metres or the apartments exceed eight, counting all phases. A state can lower these limits.

How much can a builder take before the agreement for sale?

No more than 10% of the cost of the flat, plot or building, as an advance or application fee, before a written agreement for sale is signed and registered.

What is the defect liability period under RERA?

Five years from the date of handing over possession. Defects reported in that period must be fixed free of charge within 30 days, failing which you can claim compensation.

What can I do if my flat is delayed?

You can withdraw and claim a refund with interest and compensation, or stay in the project and receive interest for every month of delay until possession, at the rate set in your state's rules.

Where do I file a RERA complaint?

With your state's Real Estate Regulatory Authority or its adjudicating officer, usually online through the state RERA portal. Compensation claims go to the adjudicating officer.

How long do I have to appeal a RERA order?

Sixty days from receiving the order, to the state Real Estate Appellate Tribunal. The tribunal may accept a late appeal if there was sufficient cause.

Sources

  1. The Real Estate (Regulation and Development) Act, 2016 (text) — Ministry of Housing and Urban Affairs
  2. Real Estate (Regulation and Development) Act, 2016: overview — Ministry of Housing and Urban Affairs
  3. Reforms in Real Estate Sector RERA-2016 (factsheet) — Press Information Bureau

This article is for information only and is not investment, tax or legal advice. Figures are from the sources linked above as of the publish or update time. Please verify with official sources or a qualified adviser before making financial decisions.